Project Integration Management

Project Quality Management

Project Human Resource Management

Project Scope Management

Project Communications Management

Text Box: Project Time Management

Project Risk Management

Project Cost Management

Project Procurement Management

PMP Knowledge Areas

Copyright© 2010 Darren Roback

Text Box: 4.1—Develop Project Charter

Inputs:
Project Statement of Work
Business Case
Contract
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Expert Judgment

Outputs:
Project Charter (Output to 4.2, 5.1, 5.2, 10.1)
Rounded Rectangle: Initiating Process Group
Rounded Rectangle: Planning Process Group
Text Box: 4.2—Develop Project Management Plan

Inputs:
Project Charter (Input from 4.1)
Outputs from Planning Processes 
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Expert Judgment

Outputs:
Project Management Plan (Output to 4.3, 4.4, 4.5, 4.6, 5.4, 5.5, 6.6, 7.3, 8.2, 8.3, 9.2, 9.3, 9.4, 10.3, 10.4)

Text Box: 4.3—Direct and Manage Project Execution

Inputs:
Project Management Plan (Input from 4.2)
Approved Change Requests (Input from 4.5)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Expert Judgment
Project Management Information System

Outputs:
Deliverables (Output to 8.3)
Work Performance Information (Output to 4.5, 5.5, 6.6, 7.3, 8.2, 10.5, 11.6, 12.3)
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Project Document Updates

Text Box: 4.4—Monitor and Control Project Work

Inputs:
Project Management Plan (Input from 4.2)
Performance Reports (Input from 10.5)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Expert Judgment

Outputs:
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Project Document Updates




Text Box: 4.5—Perform Integrated Change Control

Inputs:
Project Management Plan (Input from 4.2)
Work Performance Information (Input from 4.3)
Change Requests (Input from 4.3, 4.4, 5.4, 5.5, 6.6, 7.3, 8.2, 8.3, 9.4, 10.4, 10.5, 11.6, 12.1, 12.2, 12.3)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Expert Judgment
Change Control Meetings

Outputs:
Change Request Status Updates (Output to 4.3, 8.3, 12.3)
Project Management Plan Updates (Output to 4.2)
Project Document Updates

Text Box: 4.6—Close Project or Phase

Inputs:
Project Management Plan (Input from 4.2)
Accepted Deliverables (Input from 5.4)
Organizational Process Assets

Tools & Techniques:
Expert Judgment

Outputs:
Final Product, Service, or Result Transition (Output to Customer!!)
Organizational Process Assets Updates




Text Box: 5.1—Collect Requirements

Inputs:
Project Charter (Input from 4.1)
Stakeholder Register (Input from 10.1)

Tools & Techniques:
Interviews
Focus Groups
Facilitated Workshops
Group Creativity Techniques
Group Decision Making Techniques
Questionnaires and Surveys
Observations
Prototypes

Outputs:
Requirements Documentation (Output to 4.2, 5.2, 5.3, 5.4, 5.5, 12.1)
Requirements Management Plan (Output to 4.2)
Requirements Traceability Matrix (Output to 5.4, 5.5)
Text Box: 5.2—Define Scope

Inputs:
Project Charter (Input from 4.1)
Requirements Documentation (Input from 5.1)
Organizational Process Assets

Tools & Techniques:
Expert Judgment
Product Analysis
Alternatives Identification
Facilitated Workshops

Outputs:
Project Scope Statement (Output to 4.2, 5.3, 6.2, 6.4, 6.5, 11.1, 11.3)
Project Document Updates




Text Box: 5.3—Create WBS

Inputs:
Project Scope Statement (Input from 5.2)
Requirements Documentation (Input from 5.1)
Organizational Process Assets

Tools & Techniques:
Decomposition

Outputs:
WBS 
WBS Dictionary
Scope Baseline (Output to 4.2, 6.1, 7.1, 7.2, 8.1, 11.2, 12.1)
Project Document Updates


Text Box: 5.4—Verify Scope

Inputs:
Scope baseline (Input from 4.2)
Requirements Documentation (Input from 5.1)
Requirements Traceability Matrix (Input from 5.1)
Validated Deliverables (Input from 8.3)

Tools & Techniques:
Inspection

Outputs:
Accepted Deliverables (Output to 4.6)
Change Requests (Output to 4.5)
Project Document Updates

Text Box: 5.5—Control Scope

Inputs:
Project Management Plan (Input from 4.2)
Work Performance Information (Input from 4.3)
Requirements Documentation (Input from 5.1)
Requirements Traceability Matrix (Input from 5.1)
Organizational Process Assets

Tools & Techniques:
Variance Analysis

Outputs:
Work Performance Measurements (Output to 8.3, 10.5)
Organizational Process Assets Updates
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Project Document Updates


Text Box: 6.1—Define Activities

Inputs:
Scope Baseline (Input from 5.3)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Decomposition
Rolling Wave Planning
Templates
Expert Judgment

Outputs:
Activity List (Output to 6.2, 6.3, 6.4, 6.5)
Activity Attributes (Output to 6.2, 6.3, 6.4, 6.5)
Milestone List (Output to 6.2)



Text Box: 6.2—Sequence Activities

Inputs:
Activity List (Input from 6.1)
Activity Attributes (Input from 6.1)
Milestone List (Input from 6.1)
Project Scope Statement (Input from 5.2)
Organizational Process Assets

Tools & Techniques:
Precedence Diagramming Method (PDM)
Dependency Determination
Applying Leads and Lags
Schedule Network Templates

Outputs:
Project Schedule Network Diagrams (Output 6.5)
Project Document Updates


Text Box: 6.3—Estimate Activity Resources

Inputs:
Activity List (Input from 6.1)
Activity Attributes (Input from 6.1)
Resource Calendars (Input from 9.2, 12.2)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Expert Judgment
Alternatives Analysis
Published Estimating Data
Bottom-up Estimating
Project Management Software

Outputs:
Activity Resource Requirements (Output to 6.4, 6.5, 9.1, 12.1)
Resource Breakdown Structure 
Project Document Updates



Text Box: 6.4—Estimate Activity Durations

Inputs:
Activity List (Input from 6.1)
Activity Attributes (Input from 6.1)
Activity Resource Requirements (Input from 6.3)
Resource Calendars (Input from 9.2, 12.2)
Project Scope Statement (Input from 5.2)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Expert Judgment
Analogous Estimating
Parametric Estimating
Three-point Estimates
Reserve Analysis

Outputs:
Activity Duration Estimates (Output to 6.5, 11.2)
Project Document Updates


Text Box: 6.5—Develop Schedule

Inputs:
Activity List (Input from 6.1)
Activity Attributes (Input from 6.1)
Project Schedule Network Diagrams (Input from 6.2)
Activity Resource Requirements (Input from 6.3)
Resource Calendars (Input from 9.2, 12.2)
Activity Duration Estimates (Input from 6.4)
Project Scope Statement (Input from 5.2)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Schedule Network Analysis
Critical Path Method
Critical Chain Method
Resource Leveling
What-if Scenario Analysis
Applying Leads and Lags
Schedule Compression
Scheduling Tool

Outputs:
Project Schedule (Output to 6.6, 7.1, 7.2, 8.1, 12.1)
Schedule Baseline (Output to 4.2, 6.6, 8.1)
Schedule Data
Project Document Updates


Text Box: 6.6—Control Schedule

Inputs:
Project Management Plan (Input from 4.2)
Project Schedule (Input from 6.5)
Schedule Baseline (Input from 6.5)
Work Performance Information (Input from 4.3)
Organizational Process Assets

Tools & Techniques:
Performance Reviews
Variance Analysis
Project Management Software
Resource Leveling
What-if Scenario Analysis
Adjusting Leads and Lags
Schedule Compression
Scheduling Tool

Outputs:
Work Performance Measurements (Output to 8.3, 10.5)
Organizational Process Assets Updates
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Project Document Updates
Text Box: 7.1—Estimate Costs

Inputs:
Scope Baseline (Input from 5.3)
Project Schedule (Input from 6.5)
Human Resource Plan (Input from 9.1)
Risk Register (Input from 11.2)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Expert Judgment
Analogous Estimating
Parametric Estimating
Bottom-up Estimating
Three-point Estimates
Reserve Analysis
Cost of Quality
Project Management Estimating Software
Vendor Bid Analysis

Outputs:
Activity Cost Estimates (Output to 7.2, 11.2, 12.1)
Basis of Estimates (Output to 7.2)
Project Document Updates


Text Box: 4.1 
Develop Project Charter
Text Box: 7.2—Determine Budget

Inputs:
Activity Cost Estimates (Input from 7.1)
Basis of Estimates (Input from 7.1)
Scope Baseline (Input from 5.3)
Project Schedule (Input from 6.5)
Resource Calendars (Input from 9.2)
Contracts (Input from 12.2)
Organizational Process Assets

Tools & Techniques:
Cost Aggregation
Reserve Analysis
Expert Judgment
Historical Relationships
Funding Limit Reconciliation

Outputs:
Cost Performance Baseline (Output to 4.2, 8.1, 12.1)
Project Funding Requirements (Output to 7.3)
Project Document Updates
Text Box: 7.3—Control Costs

Inputs:
Project Management Plan (Input from 4.2)
Project Funding Requirements (Input from 7.2)
Work Performance Information (Input from 4.3)
Organizational Process Assets

Tools & Techniques:
Earned Value Management
Forecasting
To-Complete Performance Index (TCPI)
Performance Reviews
Variance Analysis
Project Management Software

Outputs:
Work Performance Measurements (Output to 8.3, 10.5)
Budget Forecasts (Output to 10.5)
Organizational Process Assets Updates
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Project Document Updates
Text Box: 8.1—Plan Quality

Inputs:
Scope Baseline (Input from 5.3)
Stakeholder Register (Input from 10.1)
Cost Performance Baseline (Input from 7.2)
Schedule Baseline (Input from 6.5)
Risk Register (Input from 11.2)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Cost-Benefit Analysis
Cost of Quality
Control Charts
Benchmarking
Design of Experiments
Statistical Sampling
Flowcharting
Proprietary Quality Management Methodologies
Additional Quality Planning Tools

Outputs:
Quality Management Plan (Output to 4.2, 8.2, 11.2)
Quality Metrics (Output to 8.2, 8.3)
Quality Checklists (Output to 8.3)
Process Improvement Plan (Output to 4.2)
Project Document Updates
Text Box: 8.2—Perform Quality Assurance

Inputs:
Quality Management Plan (Input from 4.2)
Process Improvement Plan (Input from 4.2)
Quality Metrics (Input from 8.1) 
Work Performance Information (Input from 4.3)
Quality Control Measurements (Input from 8.1)

Tools & Techniques:
Plan Quality and Perform Quality Control Tools and Techniques
Quality Audits
Process Analysis

Outputs:
Organizational Process Assets Updates
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Project Document Updates
Text Box: 8.3—Perform Quality Control

Inputs:
Quality Management Plan (Input from 4.2)
Quality Metrics (Input from 8.1)
Quality Checklists (Input from 8.1)
Work Performance Measurements (Input from 5.5, 6.6, 7.3)
Approved Change Requests (Input from 4.5)
Deliverables (Input from 4.3)
Organizational Process Assets

Tools & Techniques:
Cause and Effect Diagrams
Control Charts
Flowcharting
Histogram
Pareto Chart
Run Chart
Scatter Diagram
Statistical Sampling
Inspection
Approved Change Requests Review

Outputs:
Quality Control Measurements (Output to 8.2)
Validated Changes
Validated Deliverables (Output to 5.4)
Organizational Process Assets Updates
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Project Document Updates
Text Box: 9.1—Develop Human Resource Plan

Inputs:
Activity Resource Requirements (Input from 6.3)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Organization Charts and Position Descriptions
Networking
Organizational Theory

Outputs:
Human Resource Plan (Output to 4.2, 7.1)
Text Box: 9.2—Acquire Project Team

Inputs:
Human Resource Plan (Input from 4.2)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Pre-Assignment
Negotiation
Acquisition
Virtual Teams

Outputs:
Project Staff Assignments (Output to 9.3, 9.4)
Resource Calendars (Output to 6.3, 6.4, 6.5, 7.2, 9.3)
Project Management Plan Updates (Output to 4.2)
Text Box: 9.3—Develop Project Team

Inputs:
Project Staff Assignments (Input from 9.2)
Human Resource Plan (Input from 4.2)
Resource Calendars (Input from 9.2, 12.2)

Tools & Techniques:
Interpersonal Skills
Training
Team-Building Activities
Ground Rules
Co-Location
Recognition and Awards

Outputs:
Team Performance Assessments (Output to 9.4)
Enterprise Environmental Factors Updates
Text Box: 9.4—Manage Project Team

Inputs:
Project Staff Assignments (Input from 9.2)
Human Resource Plan (Input from 4.2)
Team Performance Assessments (Input from 9.3)
Performance Reports (Input from 10.5)
Organizational Process Assets

Tools & Techniques:
Observation and Conversation
Project Performance Appraisals
Conflict Management
Issue Log
Interpersonal Skills

Outputs:
Enterprise Environmental Factors Updates
Organizational Process Assets Updates
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Text Box: 10.1—Identify Stakeholders

Inputs:
Project Charter (Input from 4.1)
Procurement Documents (Input from 12.1)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Stakeholder Analysis
Expert Judgment

Outputs:
Stakeholder Register (Output to 5.1, 8.1, 10.2, 10.4, 11.2)
Stakeholder Management Strategy (Output to 10.2, 10.4)
Text Box: 10.2—Plan Communications

Inputs:
Stakeholder Register (Input from 10.1)
Stakeholder Management Strategy (Input from 10.1)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Communication Requirements Analysis
Communication Technology
Communication Models
Communication Methods

Outputs:
Communications Management Plan (Output to 4.2, 11.1)
Project Document Updates
Text Box: 10.3—Distribute Information

Inputs:
Communications Management Plan (Input from 4.2)
Performance Reports (Input from 10.5)
Organizational Process Assets

Tools & Techniques:
Communication Methods
Information Distribution Tools

Outputs:
Organizational Process Assets Updates
Text Box: 10.4—Manage Stakeholder Expectations

Inputs:
Stakeholder Register (Input from 10.1)
Stakeholder Management Strategy (Input from 10.1)
Communications Management Plan (Input from 4.2)
Issue Log
Change Log
Organizational Process Assets

Tools & Techniques:
Communication Methods
Interpersonal Skills
Management Skills

Outputs:
Organizational Process Assets Updates
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Project Document Updates
Text Box: 10.5—Report Performance

Inputs:
Project Management Plan (Input from 4.2)
Work Performance Information (Input from 4.3)
Work Performance Measurements (Input from 5.5, 6.6, 7.3)
Budget Forecasts (Input from 7.3)
Organizational Process Assets

Tools & Techniques:
Variance Analysis
Forecasting Methods
Communication Methods
Reporting Systems

Outputs:
Performance Reports (Output to 4.4, 9.4, 10.3, 11.6, 12.3)
Organizational Process Assets Updates
Change Requests (Output to 4.5)
Text Box: 11.1—Plan Risk Management

Inputs:
Project Scope Statement (Input from 5.2)
Cost Management Plan (Input from 4.2)
Schedule Management Plan (Input from 4.2)
Communications Management Plan (Input from 10.2)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Planning Meetings and Analysis

Outputs:
Risk Management Plan (Output to 4.2, 11.2, 11.3, 11.4, 11.5)
Text Box: 11.2—Identify Risks

Inputs:
Risk Management Plan (Input from 11.1)
Activity Cost Estimates (Input from 7.1)
Activity Duration Estimates (Input from 6.4)
Scope Baseline (Input from 5.3)
Stakeholder Register (Input from 10.1)
Cost Management Plan (Input from 4.2)
Schedule Management Plan (Input from 4.2)
Quality Management Plan (Input from 8.1)
Project Documents
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Documentation Reviews
Information Gathering Techniques
Checklist Analysis
Assumptions Analysis
Diagramming Techniques
SWOT Analysis
Expert Judgment

Outputs:
Risk Register (Output to 7.1, 8.1, 11.3, 11.4, 11.5, 11.6, 12.1)
Text Box: 11.3—Perform Qualitative Risk Analysis

Inputs:
Risk Register (Input from 11.2)
Risk Management Plan (Input from 11.1)
Project Scope Statement (Input from 5.2)
Organizational Process Assets

Tools & Techniques:
Risk Probability and Impact Assessment
Probability and Impact Matrix
Risk Data Quality Assessment
Risk Categorization
Risk Urgency Assessment
Expert Judgment

Outputs:
Risk Register Updates (Output to 11.2)
Text Box: 11.4—Perform Quantitative Risk Analysis

Inputs:
Risk Register (Input from 11.2)
Risk Management Plan (Input from 11.1)
Cost Management Plan (Input from 4.2)
Schedule Management Plan (Input from 4.2)
Organizational Process Assets

Tools & Techniques:
Data Gathering and Representation Techniques
Quantitative Risk Analysis and Modeling Techniques
Expert Judgment

Outputs:
Risk Register Updates (Output to 11.2)
Text Box: 11.5—Plan Risk Responses

Inputs:
Risk Register (Input from 11.2)
Risk Management Plan (Input from 11.1)

Tools & Techniques:
Strategies for Negative Risks or Threats
Strategies for Positive Risk or Opportunities
Contingent Response Strategies
Expert Judgment

Outputs:
Risk Register Updates (Output to 11.2)
Risk-Related Contract Decisions (Output to 12.1)
Project Management Plan Updates (Output to 4.2)
Project Document Updates
Text Box: 11.6—Monitor and Control Risks

Inputs:
Risk Register (Input to 11.2)
Risk Management Plan (Input from 4.2)
Work Performance Information (Input from 4.3)
Performance Reports (Input from 10.5)

Tools & Techniques:
Risk Reassessment
Risk Audits
Variance and Trend Analysis
Technical Performance Measurement
Reserve Analysis
Status Meetings

Outputs:
Risk Register Updates (Output to 11.2)
Organizational Process Assets Updates
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Project Document Updates
Text Box: 12.1—Plan Procurements

Inputs:
Scope Baseline (Input from 5.3)
Requirements Documentation (Input from 5.1)
Teaming Agreements
Risk Register (Input from 11.2)
Risk-Related Contract Decisions (Input from 11.5)
Activity Resource Requirements (Input from 6.3)
Project Schedule (Input from 6.5)
Activity Cost Estimates (Input from 7.1)
Cost Performance Baseline (Input from 7.2)
Enterprise Environmental Factors
Organizational Process Assets

Tools & Techniques:
Make-or-Buy Analysis
Expert Judgment
Contract Types

Outputs:
Procurement Management Plan (Output to 4.2, 12.2)
Procurement Statements of Work
Make-or-Buy Decisions (Output to 12.2)
Procurement Documents (Output to 12.3)
Source Selection Criteria (Output to 12.2)
Change Requests (Output to 4.5)
Text Box: 12.2—Conduct Procurements

Inputs:
Procurement Management Plan (Input from 4.2)
Procurement Documents (Input from 12.1)
Source Selection Criteria (Input from 12.1)
Qualified Seller List
Seller Proposals
Project Documents
Make-or-Buy Decisions (Input from 12.1)
Teaming Agreements
Organizational Process Assets

Tools & Techniques:
Bidder Conferences
Proposal Evaluation Techniques
Independent Estimates
Expert Judgment
Advertising
Internet Search
Procurement Negotiations

Outputs:
Contract (Output to 12.3)
Procurement Contract Award
Resource Calendars (Output to 6.3, 6.4, 6.5, 7.2, 9.3)
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Project Document Updates
Text Box: 12.3—Administer Procurements

Inputs:
Procurement Documents (Input from 12.1)
Procurement Management Plan (Input from 4.2)
Contract (Input from 12.2)
Performance Reports (Input from 10.5)
Approved Change Requests (Input from 4.5)
Work Performance Information (Input from 4.3)

Tools & Techniques:
Contract Change Control System
Procurement Performance Reviews
Inspections and Audits
Performance Reporting
Payment Systems
Claims Administration
Records Management System

Outputs:
Procurement Documentation (Output to 12.4)
Organizational Process Assets Updates
Change Requests (Output to 4.5)
Project Management Plan Updates (Output to 4.2)
Text Box: 12.4—Close Procurements

Inputs:
Procurement Management Plan (Input from 4.2)
Procurement Documentation (Input from 12.3)

Tools & Techniques:
Procurement Skills
Negotiated Settlements
Records Management System

Outputs:
Closed Procurements
Organizational Process Assets Updates
Text Box: 5.1
Collect Requirements
Text Box: 5.2
Define Scope
Text Box: 5.3
Create WBS
Text Box: 11.1
Plan Risk Management
Text Box: 11.2
Identify Risks
Text Box: 12.1
Plan Procurements
Text Box: 11.3
Perform Qualitative Risk Analysis
Text Box: 11.4
Perform Quant. Risk Analysis
Text Box: 11.5
Plan Risk Responses
Text Box: 10.2
Plan Communications
Text Box: 4.2 
Develop Project Management Plan
Text Box: 7.1
Estimate Costs
Text Box: 7.2
Determine Budget
Text Box: 8.1
Plan Quality
Text Box: 6.1
Define Activities
Text Box: 6.3
Estimate Activity Resources
Text Box: 6.2
Sequence Activities
Text Box: 9.1
Develop Human Resource Plan
Text Box: 6.4
Estimate Activity Durations
Text Box: 6.5
Develop Schedule
Rounded Rectangle: Executing Process Group
Text Box: 4.3 
Direct and Manage Project Execution
Rounded Rectangle: Monitoring and Controlling Process Group
Text Box: 8.2
Perform Quality Assurance
Text Box: 12.2
Conduct Procurements
Text Box: 9.2
Acquire Project Team
Text Box: 9.3
Develop Project Team
Text Box: 9.4
Manage Project Team
Text Box: 10.3
Distribute Information
Text Box: 10.4
Manage Stake- Holder Exp.
Text Box: 4.4 
Monitor and Control Project Work
Text Box: 4.5 
Perform Integrated Change Control
Text Box: 11.6
Monitor and Control Project Risks
Text Box: 12.3
Administer Procurements
Text Box: 7.3
Control Costs
Text Box: 6.6
Control Schedule
Text Box: 5.4
Verify Scope
Text Box: 5.5
Control Scope
Text Box: 8.3
Perform Quality Control
Text Box: 10.5
Report Performance
Rounded Rectangle: Closing Process Group
Text Box: 12.4
Close
Procurements
Text Box: 4.6 
Close Project or Phase
Text Box: 10.1
Identify Stakeholders

PMP Process Diagram