February 2011 CLIPBOARD
UPDATES FROM FACILITIES MANAGEMENT
www.siue.edu/FACILITIES
Service Alerts &
Activities
Vadalabene Center Pool
Failure of the pool heater resulted in some “cold
swims.” The replacement should be installed and the pool back
up to normal by the first of next week.
Question from Facilities Management’s Web Page
Note: On the Facilities Management Web Page, visitors
are asked to leave questions or comments; this is the most recent.
Suggestions: When will you be re-installing the ceiling
in the basement hallway of Alumni hall (and other halls of Alumni as
well)? They've been gone almost a year now and their absence makes the
hall look bad. Please make a public statement about this so we have
some idea when you will restore our building. Thanks.
Answer: The hiring freeze as well as changes in the extra
help rules have caused Facilities to have to reprioritize a much more
limited labor pool. Work on the ceilings was delayed as projects with
more pressing time lines were completed. We have been back on the ceiling
project for a couple of weeks and are looking to finish the project
by the start of fall classes.
Robert B. Washburn
Director Facilities Management
Southern Illinois University Edwardsville
(618)650-2560 - fax (618)650-2595
Projects
Window Upgrades
When campus was originally designed, energy was cheap
and plentiful and the expense of double pane or insulated glass windows
was considered an extravagance. However, today energy costs are increasing
and the University continues to pursue methods to reduce those costs.
Obviously, replacement of the single pane windows would be a big help,
but the cost of replacement can be expensive. Construction documents
have been completed by the architects and are being reviewed by the
University. They are out for bid and the results will be received in
late February. Design concepts have begun for window replacement at
Rendleman Hall and those ideas should be provided to the University
in a few months. Dunham Hall is under a State design contract through
the Capital Development Board (CDB) and work moves per their requirements
which are slower than the University’s procedures. Work on Peck
Hall is anticipated to start following May commencement with critical
classroom spaces to be done over the summer. The University has been
promised that lobby window replacement in Dunham Hall will also begin
this summer and extend into the fall. No construction schedule has yet
been developed for Rendleman Hall.
Science Lab Building West
Construction work was delayed several weeks when the drill rig blew
its engine. When another drill rig was located and moved to the site,
it was assembled and found to have some problems, but those have been
corrected and drilling has resumed. More than 350 of the augers have
been drilled out of the 537 planned. Site adjustment work has begun
and many dump trucks have been rolling in and out of the site. The contractor
has tied down the construction schedule and all subcontractors have
agreed with the proposed schedule which calls for completion in mid-May
2012. Once finished, move in will begin and should be complete for the
fall semester. The existing building will be renovated after the addition
is complete; the CDB is currently negotiating with the architects and
engineers for bid documentation of the renovation.
Engineering Building Addition
The schematic design has been presented to the University and work has
begun on the design development phase. The schematic phase applies the
programmatic needs the University stated to the Architects to a floor
plan to develop spaces and relationships between the various users.
The users review the plan to see if it fulfills their needs and ample
opportunity is allowed for them to suggest alternative ideas or to critique
the plans. Concepts of the exterior design and a rough estimate of costs
are also provided for review and comment. This project is not as well
developed as several others as it was on hold for several months. Current
plans call for completion of the facility for fall, 2012.
Vadalabene Center Addition
Architects and engineers are developing construction documents (specifications
and drawings) for the 2-story-plus basement addition to the north end
of the Vadalabene Center. The Athletics Department will move its operation
to the first floor of this new space and use the basement as a weight
training area. The upper level is unfinished presently and will be available
when other needs occur. Once Athletics moves from its current location,
Kinesiology will be able to expand into the vacated spaces. This project
is also on schedule for opening in the fall of 2012.
Morris University Center
New first floor restrooms have been open since the fall semester and
have been well received. The Center will update and expand Pizza Hut
and Taco Bell operations this summer. The front of Pizza Hut will be
expanded to align with the front of Taco Bell. This expansion will improve
the working space but, more importantly, will allow for the addition
of Wings Street to Pizza Hut. The Taco Bell work area is also being
revised to improve the operation and possibly allow some menu additions.
The Center is exploring the cost and work to replace the HVAC units
throughout the building. New units would be more energy efficient and
reliable; it is a matter of determining the best course of action and
paying for the work.
Art & Design
Architects and engineers continue to make progress on preparing bid
documents. These documents will require the Board Architects review
and comments before they are issued for bidding. At this time, the bid
documents are for the addition only. Once the addition is complete (another
fall 2012 anticipated completion), then the renovation of the existing
building will begin. The building will be occupied during renovation,
so open areas are needed and operations moved into the new addition
will provide the needed free space.
Heating & Refrigeration Plant
The concrete infill over two large holes in the floor has been completed.
Engineering students have re-occupied the space to continue their work
on the solar car, Formula One cars, concrete canoes and bridges. Much
more space is now available to the students, plus they now have a raised
platform for the work area to ease some of the work along the side of
their projects.
Baseball
The locker room work has been completed and a few punch list items remain.
The building is ready for use when the baseball season begins. Unfortunately,
the weather has not cooperated and the turf replacement project is stymied
by the ice and snow. Once that has melted away, the contractor can resume
his installation. Hopefully, the first game on home turf is a winner!
Alton Campus
With the exclusion of four tract houses, the windows have been replaced
in all buildings on the Alton Campus. The windows have greatly improved
weathertightness and reduced energy consumption as insulated glass replaced
single pane glass. The staff must be happier, especially this winter,
since the windows have improved their comfort in these severe temperatures.
Renovation of the Science Building basement corridor has begun. Work
is primarily visual improvements but new lighting and HVAC will make
the space more comfortable and match the recently renovated computer
study center adjacent to this corridor. New lockers will enhance the
student’s use of the adjacent computer work/study center. Another
small construction project that was bid and released for construction
this spring is a gift of the class of 2011. Watch for reports of this
gift.
ESLHEC
The Capital Development Board issued a change order to complete the
fence and gate replacement project. Weather was also a factor in completion
of this work. Unfortunately, a concrete contractor installed the new
sidewalk with the ADA ramp incorrectly, so when the better weather returns,
that will have to be replaced. Gatekeepers to hold the gates against
the support posts when opened have been installed and several other
touch up items have also been completed.
MISCELLANEOUS PROJECTS
Other miscellaneous work on campus includes replacement
of some doors at Alton. New furniture is being installed in public areas
from time to time; ceilings and lighting are being upgraded in many
areas (such as the open stairwell area of Peck Hall where completion
of new ceilings and lighting took place last summer). Many of the items
are not readily apparent, but would definitely be noticeable if they
were not completed. A painting program is in place to allow for painting
of classrooms during non-use periods (between semesters or over the
summer); door hardware is being replaced and upgraded; new closers and
operators are being installed on entry doors, and many other routine
maintenance projects like upgrading of HVAC systems and plumbing are
ongoing. SIUe is, after all, the equivalent of a small city!
SERVICE NUMBERS
FACILITIES MANAGEMENT SERVICES
Temperature Control, Work Order Control, Customer Service/650-3711
Key Control/650-3200
Utilities & Energy Management/650-3329
Grounds/650-2719
Director/650-2560
Business Manager, Alicia Wainright/650-3161
OPERATIONAL MANAGERS:
Janice LaRiviere/650-3804 (Maintenance)
Steve Brandenburg/650-2069 (Building Services, Grounds)
Ed Matecki/650-2258 (Utilities)
Frank Zaloga/7252 or 6350 (Alton SDM and ESLHEC)
Architects/Engineers:
Rick Klein/650-3575
Mohammad Rouf/650-3917
Patrick Long/650-2810
Facilities Management Fax: 618-650-2595
After hours/week-end building problems: 650-3324