![]() ![]() ![]() |
||||
|
CLIPBOARD
April 15th - 21st, 2007 WEEKLY UPDATES FROM FACILITIES MANAGEMENT "Life’s Lessons 3" just before the Service Numbers
"The optimist proclaims that we live in the best of all possible worlds; the pessimist fears this is true." James Branch Cabell WHAT’S NEW? NORTH UNIVERSITY DRIVE IS OPEN! The barricades are down and some warning signs still need to be removed, but the road is officially open. Drivers are reminded to drive carefully in the area since the road is different and new asphalt can be very slick, especially when wet with dew, frost or rain. THE CURRENT KEY TO ACCESS--REMINDER IN
THE WORKS
CAMPUS GOING KEYLESS Remaining buildings:
MASONRY RENOVATION
Update April 15, 2007: The contractor arrived this week as promised and has begun cleaning up remnants of his work. Facilities moved some of the brick pallets at the request of the contractor; he estimates it will take three weeks to complete his work. However, the work is weather dependent and could be delayed by rain or cold weather. MASS RELAMP Update April 15, 2007: Lamps are currently being changed in the Science Building. Work has moved a little slower as the electricians encounter more ballasts that need changed as well as lights. Naturally, since the re-lamp started 18 months later than scheduled, there will be “hot spots” where lamps have already burned out. Electricians will continue to address these problems; report any dark spaces to Customer Service at 3711. EAST ST. LOUIS HIGHER EDUCATION CENTER (ESLHEC) Update April 15, 2007: One contractor on campus to pour sidewalks was delayed by the unexpected cold weather; the weather forecast calling for rain next week could also prevent his work. The window contractor has submitted and received approval on the window replacement units and ordered them. When school is dismissed in May, the new windows should be on site and replacement will begin. The other current project in design is the replacement of lintels and tuck pointing of the brick walls. The 100% Review Documents have been submitted and are undergoing review. CDB will compile all the comments and send them to the architects for their response and drawing modifications. ADA PROJECT Update April 15, 2007: Excavation for the elevator building addition on 8280 in Alton is progressing. Concrete support slabs have been poured, and the contractor is preparing to excavate and form the footings. Brick and stone samples are being reviewed to select a match to the exterior of the existing building. The electrical contractor is concentrating on the fire alarm system in the Vadalabene Center. SCIENCE BUILDING Update April 8, 2007: A meeting with the architects and lab designers is being scheduled for the end of April. Principally, the discussions and review will be centered on the proposed laboratory layouts. Some discussion of the classrooms and faculty offices may take place if time permits. Once the laboratories are generally determined, the architects will begin to determine locations of the departments including classrooms, faculty offices, the laboratories and related spaces. LIFE’S LESSONS
-3-
SERVICE
NUMBERS FACILITIES MANAGEMENT SERVICES
Temperature Control, Work Order Control, Maintenance Calls/650-3711 Building Services (Custodial)/650-2067 Customer Service/650-3711 Key Control/650-3200 Utilities & Energy Management/650-3329 Grounds/650-2719 Director/650-2560 Billing Inquiries/650-3161 East St. Louis Higher Education Campus/874-8716 IMPORTANT INDIVIDUAL NUMBERS Architects/Engineers: Rick Klein/3575 Mohammad Rouf/3917 Dan Runyon/3349 Don Anderson/2567 Billing: Alicia Wainright/3161 Operational Managers: Janice LaRiviere/3804 (Maintenance) Steve Brandenburg/2069 (Building Services, Grounds) Ed Matecki/3329 or 2258 (Utilities) Customer Service/Facilities Management /Phone: 618-650-3711 Facilities Management Fax: 618-650-2595 After hours/week-end building problems/3513 As always, for maintenance concerns, temperature problems, or to place a work order, phone extension 3711. |
|||
|
URL:
http://www.siue.edu/FACILITIES/clipboard/clipboard.htm
Published by: Facilities Management Last Update:18 October, 2007 Send Comments to: fmserv@siue.edu |