|
Site
Map
|
CLIPBOARD
September
24-30, 2006
WEEKLY UPDATES
FROM FACILITIES MANAGEMENT
“Ways
to
deal with Insanity” just before the Service Numbers
"A couple years ago they told me I was too young to be
president and you were too old to be playing baseball. But we fooled
them."
President John F. Kennedy to Stan Musial at the 1962 All Star
Game
WHAT’S
NEW?
RAMP CLOSINGS
As the retaining
wall at the south end of Founders Hall is rebuilt, the ramp will be
closed beginning Monday, September 25, 2006. It will remain closed
until work is complete, probably through Thursday, September 28, 2006.
Once the work at Founders Hall is complete, the rebuilding of the
retaining wall at the north end of Alumni Hall will begin. The
scheduling of work at Alumni Hall will be shared with the University
community when it is known.
FM FORUM
Once again, FM
is receiving a spate of calls about bagged toilets in restrooms. FM
relies on Building Service Workers, Building Engineers, and number of
other people to report these problems, but it is impossible for these
folks to be everywhere all the time. Please, please report bagged or
problem toilets as soon as possible; better to report a problem three
or four times than (as most of you know) to let it go until it smells
bad. FM greatly appreciates the assistance of building occupants.
THEY ALSO SERVE…
Divers
from American Underwater Construction completed their work in Cougar
Lake on Saturday, September 9, 2006, and were given all the credit in
the ClipBoard for working 15-25 feet underwater to recover the screen
and frame. However, as Ed Matecki, Assistant Director for Utilities,
mentioned, it was SIUE Engineers Dennis Tate and John Lopez who worked
on the shore to help with maneuvering and modifying the screens and
assisting the divers. Good job, Dennis and John!
ENGINEERING BUILDING
On a clear
day, you can see forever, that is, unless you are looking through some
of the windows in the Engineering Building. A number of windows have
developed a foggy appearance and since they are still under warranty,
the glass panel manufacturer is responsible for providing new ones.
However, everyone involved is concerned about the reason the panels are
failing. A meeting was held with the glass panel manufacturer, the
curtain wall system supplier, the installer, the architect, and a
curtain wall specialist consultant. It was determined that testing of
the panels and the installation was needed to find the reason for the
problem. Currently, the tests are scheduled for September 27, 2006; if
the test has to be rescheduled, information will be sent to the faculty
and staff at the Engineering Building. Tests will include water tests
on the panels in place and removal of four of the glass panels for
further testing. Replacement glass will be installed as each of the
four panels is removed.
IN
THE WORKS
ADA PROJECT
Update
September 24, 2006: CDB reviewers have completed
their reviews and the comments have been sent to the
Architect/Engineer. Minor corrections remain; however, one CDB reviewer
has still rejected the submission. The CDB project manager is trying to
resolve the problem and a meeting will be held with the A/E and CDB
within the next few weeks to discuss the final corrections.
MASONRY
RENOVATION
Update
September 24, 2006: There is
nothing worse than starting an update with bad news. FM has been
waiting for delivery of the newly manufactured brick and on the day the
brick was to be delivered, the manufacturer called. They actually made
the brick the wrong size! Standard size brick can be one of two
lengths: 7-5/8” or 8”. The 3/8”
difference doesn’t seem like very much, but to insert a
shorter brick into a wall of longer brick, the joints have to be
widened and the end result would not look right. Thus, the brick had to
be rejected. The manufacturer is studying the production schedule and
they anticipate delivery of the correct brick around October 10, 2006.
Even after this bad news, there was some good: the brick on Founders
and Alumni Halls is the 7-5/8” size, so repair of the
retaining wall will proceed. The accessible ramp on Founders Hall will
be closed during the repairs, but should be opened by Thursday or
Friday, September 28th or 29th. Work on the retaining wall at Alumni
Hall will begin when that work is complete.th.
The masons can continue their prep work, but may have to leave for a
few
days. Their storage trailer in the accessible parking lot
just west
of Dunham Hall will be removed within the week. They are
making an
effort to unload it and will bring one of their trailers on
site.
The current storage container is a rental unit, and the agency that
owns
it has to come and pick it up with a roll-back truck.
MISCELLANEOUS
GIR/MOD PROJECTS
Update September 24, 2006:
Update September 24, 2006: The
work on the Metalsmithing area is progressing. A new door frame with
double doors was added, and to the credit of FM crafts, it is
impossible to tell where the original wall starts and stops; it blends
in beautifully. Electricians have begun placing the wiremold, the
horizontal strip on the wall that holds electrical outlets. Contractors
for the sheet metal work are preparing bids for review. Progress is
slowly moving ahead.
The atrium in the Art & Design Building will have the old
planter area filled in with a platform that will be used for display.
Also planned is a storage area under the open stairway.
Work has resumed in Building 8272, SIUE SDM Alton, as two accessible
bathrooms are created for the facility. Other building modifications
include widening of several doorways, removal of some room dividers,
installation of new flooring, and relocation of some X-ray equipment. A
meeting was held with the Architects and Engineers to discuss plans to
expand the sterilization area within the Clinic. In order to begin
construction before Christmas, the design will move at a fast pace.
Even though some work is not scheduled until the three week close down
next July, much preparation has to take place first. The required work
would prevent the clinic from serving clients, so it is scheduled when
patients are not usually using the facility.
EAST ST.
LOUIS HIGHER
EDUCATION CAMPUS (ESLHEC)
Update
September 24, 2006:Good
news for ESLHEC: the bids received for the emergency window replacement
project were very good. CDB will be issuing a contract to the low
bidder and hopefully, work can be completed before winter begins. Once
a schedule is received, it will be shared.
WAYS TO DEAL WITH INSANITY
- At
lunchtime, sit in your parked car with sunglasses on and point a hair
dryer at passing cars to see if they slow down.
- Every
time someone asks you to do something, ask if they want fries with
that.
- Put
your garbage can on your desk and label it “In.”
- Put
decaf in the coffee maker for three weeks. Once everyone is over
their caffeine addictions, switch to Espresso.
- In
the memo field of all your checks, write “for smuggling diamonds.”
- Put
mosquito netting around your work area and play tropical sounds all
day.
- Five
days in advance, tell your friends you can’t attend their party because
you’re not in the mood.
- When
the money comes out the ATM, scream, “I won! I won!”
- When
leaving the zoo, start running towards the parking lot, yelling, “Run for
your lives! They’re loose!”
- Tell
your children over dinner, “Due to the economy, we are going to have to
let one of you go.”
FACILITIES MANAGEMENT SERVICES
Temperature Control, Work Order Control, Maintenance Calls/650-3711
Building Services
(Custodial)/650-2067
Customer Service/650-3711
Key Control/650-3200
Utilities & Energy Management/650-3329
Grounds/650-2719
Director/650-2560
Billing Inquiries/650-3161
East St. Louis Higher Education Campus/874-8716
IMPORTANT INDIVIDUAL NUMBERS
Architects/Engineers:
Rick Klein/3575
Mohammad Rouf/3917
Dan Runyon/3349
Don Anderson/2567
Billing:
Alicia Wainright/3161
Operational Managers:
Janice LaRiviere/3804 (Maintenance)
Steve Brandenburg/2069 (Building Services, Grounds)
Ed Matecki/3329 or 2258 (Utilities)
Janice LaRiviere/7252 (SDM/Alton)
Customer Service/Facilities Management /Phone: 618-650-3711
Facilities Management Fax: 618-650-2595
After hours/week-end building problems/3513
As always, for maintenance concerns, temperature problems, or to place
a
work order, phone extension 3711.
|