EdwardsvilleFacilities ManagementFM Logo
Leftp
Rightp

 

 

 

 

 


Work Order Status Report

Site Map


CLIPBOARD
June 4-10, 2006
WEEKLY UPDATES FROM FACILITIES MANAGEMENT

“Interesting Headlines” just before the Service Numbers

My fiancé and I are having a little disagreement. What I want is a big church wedding with bridesmaids and flowers and a no-expense-spared reception; what he wants is to break off our engagement.
Sally Poplin


WHAT’S NEW?

SO THAT’S WHAT THAT IS!
A massive generator was delivered and set in place at Dunham Hall on Wednesday, May 31, 2006.  The generator will supply emergency power and cooling to OIT, the main Telecom switch room and the Radio Station.  The 900 amp, 480 volt, 900 horsepower, diesel-powered generator measures (approximately) 25 feet long by 8 feet wide by 12 feet high and holds 500 gallons of fuel!


NO MORE GLOOMY STAIRWELLS
Stairwell fixtures have been replaced in the Science Building as part of the Illinois Clean Energy Grant won by FM’s Ed Matecki, Assistant Director for Utilities.  The improved fixtures not only look better; they are using less energy.  Eventually, new stairwell fixtures will be installed in all campus buildings.  What a bright idea!
 

AGAIN, SADLY…
Campus flags flew at half-staff on Friday, June 2, 2006, to honor Caleb A. Lufkin, 24, Private First Class, United States Army, from Knoxville, Illinois, who died May 25, 2006, in the war in Iraq.

SO MUCH HELP…
Again in 2006, the Facilities Management Walk-Throughs are providing valuable insight into each building’s unique set of problems. The Walk-Through of the Engineering Building is scheduled for Friday, June 9, 2006.  Minutes of each Walk-Through are posted on the FM web page at www.siue.edu/FACILITIES.

ROOF RENOVATION
The renovation of Peck Hall roof has begun and should take three to four weeks to complete.

VACATION E-MAIL ADDRESSES
The departmental email accounts below should be used when sending email to Facilities Management, especially during summer months when individuals may be on vacation. If an email is for a specific individual, and it doesn’t matter how soon it is answered, individual email addresses are fine. However, when the email has to do with a situation that needs to be addressed in a timely manner, the following email addresses should be used:

Hot or cold calls: E-mail (fmworks@siue.edu) or call 3711
Customer Service: E-mail (fmserv@siue.edu) or call 3711
Work Order Control: E-mail (fmworks@siue.edu) or call 3711



IN THE WORKS

NOTE: Rick Klein will not be providing updates for the next two weeks as he takes vacation to walk his daughter down the aisle.

SCHOOL OF PHARMACY
Nine months after Substantial Completion, a walk-through of the facility was conducted.  Primarily, warranty items were checked, but problems that may have developed as the building was used and as the seasons changed were also looked for.  A one year warranty on the building is in place to present an opportunity to “test drive” the building through all seasons.  (For example, the heating system may work great, but the air conditioning might not be set right.)  A few minor problems were identified on the walk, and the appropriate contractors will return to make the proper corrections.

ADA PROJECT
Update June 4, 2006:  Next on the agenda is a conference call between the architects, engineers, CDB and the University.  The architects and engineers want to ensure that they fully understand each comment from the review process and discuss alternate ideas as needed.


SIUE SDM ALTON CAMPUS/DENTAL CLINIC FACILITY EXPANSION
Update June 4, 2006:   The final clean up of the parking lot and site have been completed.  A few miscellaneous questions remain, and the architects and engineers are reviewing the contractor’s responses.  Once those issues are determined, contractors will complete their final work.  The Dental School is assembling and installing the dental chairs, X-ray equipment, and other smaller equipment items.

MASONRY RENOVATION
Update June 4, 2006:   The masonry contractor won’t be seen on site much this summer.  He has completed most of his work with the exception of brick replacement on Lovejoy Library, Peck, Founders and Alumni Halls.  The brick manufacturer has promised delivery of the correct bricks by the first of August, so the contractor is completing odds and ends while awaiting the arrival of the bricks.

MISCELLANEOUS GIR/MOD PROJECTS
Update June 4, 2006:   The contractor will be pouring the concrete slab behind the Art & Design Building very soon.  A study for a low wall around the concrete slab has slightly slowed the construction work; a decision has been made for the contractor to make a minor adjustment to his slab edge to allow for the wall.  This wall will be brick and block; the work will await the brick currently being manufactured for the Masonry Renovation project.  Another Art & Design project involves the Graduate Painting and Textiles Studio, where a new partition system has been designed to alleviate the cluttered and cramped current conditions. 

The conversion of an old classroom to a dispensing area begins next week at the Alton Dental Clinic.  Some doors will be closed, a double door will be installed, and two half window openings will be installed in the corridor to facilitate pick up of dental work trays.

EAST ST. LOUIS HIGHER EDUCATION CAMPUS (ESLHEC)
Update May 28, 2006: Some small projects are ready to move forward, but delayed by unforeseen circumstances.  For example, the company that installed the fence returned to repair and repaint portions of it, but went bankrupt before completing the repairs.  Now, CDB has legal issues to resolve before another contractor can be hired.  Ceiling replacement in the cafeteria will take place after the exhaust fan in the grill hood is replaced and the exterior water leaks are fixed.  Preliminary plans for the exterior work package have been submitted for review, though, so some progress is being made.




Include Your Children when Baking Cookies
Something Went Wrong in Jet Crash, Expert Says
Police Begin Campaign to Run Down Jaywalkers
Safety Experts Say School Bus Passengers Should Be Belted
Drunk Gets Nine Months in Violin Case
Survivor of Siamese Twins Joins Parents
Iraqi Head Seeks Arms
Eye Drops Off Shelf
Miners Refuse to Work after Death
Two Sisters Reunited After 18 Years in Checkout Counter




SERVICE NUMBERS

FACILITIES MANAGEMENT SERVICES
Temperature Control, Work Order Control, Maintenance Calls/650-3711
Building Services (Custodial)/650-2067    
Customer Service/650-3711
Key Control/650-3200
Utilities & Energy Management/650-3329
Grounds/650-2719
Director/650-2560
Billing Inquiries/650-3161
East St. Louis Higher Education Campus/874-8716

IMPORTANT INDIVIDUAL NUMBERS
Architects/Engineers:
Rick Klein/3575
Mohammad Rouf/3917
Dan Runyon/3349
Don Anderson/2567

Billing:
Alicia Wainright/3161

Operational Managers:
Janice LaRiviere/3804 (Maintenance)
Steve Brandenburg/2069 (Building Services, Grounds)
Ed Matecki/3329 or 2258 (Utilities)

Customer Service/Facilities Management /Phone: 618-650-3711
Facilities Management Fax:  618-650-2595
After hours/week-end building problems/3513
As always, for maintenance concerns, temperature problems, or to place a work order, phone extension 3711.




 
URL: http://www.siue.edu/FACILITIES/clipboard/clipboard.htm
Published by: Facilities Management
Last Update: 1 November, 2007
Send Comments to: fmserv@siue.edu